Year 12 – Standard 2

Critical path analysis
  • Construct a Loading  diagram from a Loading  or equivalent, including those involving Loading , limited to 10 activities

  • Explain the term Loading 

  • Apply Loading  and Loading  to determine the Loading  and Loading  for each activity in a project

  • Calculate Loading  to identify Loading  and Loading 

  • Analyse ESTs and LSTs to locate the critical path(s) for the project

  • Apply critical path analysis to determine the minimum completion time for a project

  • Construct a Loading  to represent a project from a network diagram indicating the critical path

  • Examine the impact of increasing or reducing the duration of an activity on the completion time of the project or task being modelled

  • Use a spreadsheet to model a project involving precedence tables and solve related problems